Pounding Mill Quarry
RailWorks constructed new track infrastructure to improve efficiencies at the Pounding Mill Quarry.
- Constructed 7,400-ft. new track
- Constructed 40-ft steel span bridge
- Installed new crossing with signal protection
Bluefield, VA
Customer
Pounding Mill Quarry Corporation
RailWorks Business Unit
RailWorks Track Services
Description
RailWorks completed the new track construction project to accommodate more efficient operations at the limestone quarry.
Scope
RailWorks constructed 7,400 feet of new track, installed 4 turnouts, built a new 40-foot steel span bridge with concrete headwalls and timber deck boards, and constructed a 100-foot timber and asphalt road crossing with new warning lights and gates.
Unique features
The new track infrastructure provides an efficient network for inbound and outbound Norfolk Southern trains servicing the limestone quarry.