The Millennium Line SkyTrain
Extension
 |
 |
| Completed
in 2002, the Millennium
Line is a 20km expansion
to Vancouver's SkyTrain.
PNR completed 40,000
linear meters of track,
LIM and power rail installation. |
|
 |
 |
Customer
Rapid Transit Project 2000,
Ltd.
Location
Vancouver, British Columbia
RailWorks Company Involved
PNR (Pacific
Northern Rail Contractors, Inc.)
Project Manager
Peter Pearce
Project Scope
PNR is notable among builders of the
20-kilometer (12.4 miles) expansion
to Vancouver’s SkyTrain
rapid transit system, the Millennium Line. The Millennium Line begins
in New Westminster and extends west to near Vancouver Community College.
Like SkyTrain’s original Expo Line, the Millennium Line eases
traffic congestion in the Lower Mainland, where the population is
expected to double in the next decade, and continues Greater Vancouver’s
commitment to reducing air and noise
pollution.
PNR crews began their work in April
2000 and finished in February 2002 — months ahead of schedule.
Up to 350 people were working during
peak phases. They:
- Expanded the existing maintenance and
service facility tracks, which
included installing about 1,600
linear meters of new concrete tie
track and 10 switches.
- Installed the trackwork (40,000 linear
meters), as well as 40 pieces
of special trackwork including No. 8 lateral turnouts and expansion joints.
- Installed
the LIM reaction rail.
- Put in the
power rail.
Project Challenges and RailWorks Solutions
Elevated
Guideway Calls for Careful Planning
Because much of the Millennium
Line is on an elevated guideway, workers and equipment
were virtually always 25 feet above the ground. Says
Pearce, “When you add to that the fact that your
work area was only eight and a half feet wide and that
it was down in the middle of major arterial roads, the
access was a challenge. And in that space, there’s
not much opportunity to switch the position of equipment.
Servicing our equipment was a challenge, too. Organization
and planning were the key.”
A Linear Operation Means
No Room for Delay
In a project of this nature, many
operations are dependent upon the ones before them.
If one process takes too long, it delays the entire
project. Instead, utilizing an experienced worker pool
and innovative solutions, PNR was able to work well
ahead of schedule.
PNR’s workers were typically
innovative on this project. They designed and built
a complete flash butt
welding system to operate in the
narrow guideway. To speed the drilling processes for
the LIM and power rail
system, they developed specialty
coring equipment and environmentally sound means of
dealing with the coring
sediment.
Team of 10 Leads Quality
Process
The Millennium Line was built to
ISO-9000 standards. Out of 40 PNR staff, 10 were responsible
for quality control. So wherever the specification gave
a tolerance, it was checked and logged. Pearce called
the quality records “massive.”
“
Quality is an investment, but it’s an important
one,” he says. “The work was performed with
unparalleled quality, yet within budget and ahead of
schedule.”
PNR
PNR (Pacific Northern Rail Contractors
Inc.), a subsidiary of RailWorks
Corporation, is Canada’s
largest railroad contractor.
PNR provides complete construction
services, material supplies and
specialized railway equipment to Class 1 and short
line railroads, transit authorities
and industrial
facilities worldwide. Projects
range from industrial spurs to
transit rail and freight lines.
|
|