Aux Sable USA – Channahon Rail Yard

Building a new rail yard for Aux Sable at its Channahon Facility in Illinois enhanced the company’s car storage and switching capabilities.
Project Highlights 
  • Constructing more than 17,000 feet of track, 17 turnouts and 17 track bumpers
  • Constructing five grade crossings
  • Performing grading, drainage and electrical work
Track
Morris, Illinois
Customer 
Aux Sable USA
Business Unit 
RailWorks Track Services
Project Description 

RailWorks built a new rail yard at Aux Sable USA’s natural gas liquids (NGL) plant in Morris, Ill.

Project Scope 

RailWorks served as general contractor on the $6 million Channahon Facility project. Work got under way in October 2010, and improvements include grading, drainage, track and turnout construction, and electrical work.

RailWorks crews removed 1,600 feet of track and two turnouts and constructed 17,800 feet of track, 17 turnouts, 17 track bumpers and five grade crossings. Other site work included importing nearly 200,000 cubic yards of material for fill, installation of site power for lighting and security gate operations, 4,000 feet of security fencing, culvert installations and abandonments, and the installation of pipeline protection pads for tracks crossing underground pipelines.

Unique Features 

The project enabled Aux Sable to store and switch 150-plus rail cars on their own track property.