Project Highlights 
  • Served as general contractor for design-build project
  • Constructed 12,800 feet of track
  • Installed 13 turnouts
  • Is there bullets for this project
Track
Mayfield, Kentucky
Customer 
Progress Rail Services
Business Unit 
RailWorks Track Services
Project Description 

RailWorks served as the general contractor for this turnkey design-build project for a new yard and lead track at Progress Rail’s locomotive repair facility.

Project Scope 

RailWorks constructed 11,000 track feet on wood ties, 1,800 track feet on steel ties embedded in concrete and installed 13 turnouts and one mainline turnout on the P&L Railroad. The crew also installed the track for four locomotive inspection pits.

Unique Features 

Progress Rail purchased a site with an existing 600-foot manufacturing building to perform locomotive tear-down and rebuilding work. RailWorks designed a track system that utilized the existing building to efficiently service locomotives. The design featured three tracks extending the length of the building.

Other participants 
Subcontractor: Design 9