Work included
Replace 12,275 mainline timber ties
Undercut and Rebuild 2,530 TF
Rehab 12 turnouts(100% ties and plates)
Replace 52 IJs
Remove hair pins and install track spikes on all ties for 38,600’ of track
Surface 38,600’ of track and 14 Turnouts
Destress 38,600’ of track
Remove and Install Impedance Bonds
Install new negative return for Puritas Interlocking
Install new negative return for Brookpark Shop