Nova Biosource Fuels, Inc.

Project Highlights

  • Constructed 6,000 feet of new track
  • Installed five turnouts
  • Constructed four grade crossings
Customer
Nova Biosource Fuels, Inc.
Location
Seneca, Illinois
Provided By

RailWorks constructed the track infrastructure for the $68 million refinery at Seneca, Ill.

RailWorks built 6,000 feet of track and installed four #8 turnouts, one #10 turnout, one double switch point derail and four rubber grade crossings. RailWorks coordinated with CSX, the servicing railroad, to address requirements for the facility’s track infrastructure.

Unique Features

RailWorks completed the project on time. The new facility has the capacity to produce 60 million gallons of fuel from locally generated, low-cost feedstocks.